Description
The sidewalk at Calumet Parkway and Stony Oak Drive is incomplete. Why the city/county allowed a developer to not complete the sidewalk is a mystery. There is about 35 feet of grass between two sidewalks. The sidewalk needs to be installed or a ADA curb cutout completed at the end of the existing sidewalk.
11 Commentaires
Newnan, Georgia (Utilisateur inscrit)
rwhatzo (Utilisateur inscrit)
Newnan, Georgia (Utilisateur inscrit)
Reconnu City Engineer (Utilisateur inscrit)
Thanks for reporting.
"Back in the day", a developer was required to build sidewalk with each lot. This particular lot is associated with HOA property, not a house.
Today, we require a developer to build sidewalk on open space prior to street acceptance, to avoid this specific issue. We still have a few similar places around Newman.
We will schedule sidewalk construction for this location.
rwhatzo (Utilisateur inscrit)
rwhatzo (Utilisateur inscrit)
rwhatzo (Utilisateur inscrit)
City Engineer (Utilisateur inscrit)
rwhatzo (Utilisateur inscrit)
rwhatzo (Utilisateur inscrit)
Clos Newnan GIS (Utilisateur inscrit)